West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-12-2021
Updated as on 12-02-2022

Booking Status

  • Residential Apartments Booked
    252

  • Basement Parking Booked
    30

  • Open Car Parking Booked
    44

  • Covered Car Parking Booked
    128

  • Mechanical Parking Booked
    44

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
11 1 Under Construction
11 2 Under Construction
11 3 Under Construction
11 4 Under Construction
11 5 Under Construction
11 6 Under Construction
11 7 Under Construction
11 8 Under Construction
11 9 Under Construction
11 10 Under Construction
11 11 Under Construction
11 12 Under Construction
11 13 Under Construction
11 14 Under Construction
12 1 Under Construction
12 2 Under Construction
12 3 Under Construction
12 4 Under Construction
12 5 Under Construction
12 6 Under Construction
12 7 Under Construction
12 8 Under Construction
12 9 Under Construction
12 10 Under Construction
12 11 Under Construction
12 12 Under Construction
12 13 Under Construction
12 14 Under Construction
15 1 Under Construction
15 2 Under Construction
15 3 Under Construction
15 4 Under Construction
15 5 Under Construction
15 6 Under Construction
15 7 Under Construction
15 8 Under Construction
15 9 Under Construction
15 10 Under Construction
15 11 Under Construction
15 12 Under Construction
15 13 Under Construction
15 14 Under Construction
16 1 Under Construction
16 2 Under Construction
16 3 Under Construction
16 4 Under Construction
16 5 Under Construction
16 6 Under Construction
16 7 Under Construction
16 8 Under Construction
16 9 Under Construction
16 10 Under Construction
16 11 Under Construction
16 12 Under Construction
16 13 Under Construction
16 14 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilites
2 Electrical Installation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lift
2 Under Construction Lobby
3 Under Construction Roof
4 Under Construction Septic tank
5 Under Construction Under-ground water reservoir
6 Under Construction Overhead tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download