West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-03-2021
Updated as on 13-04-2021

Booking Status

  • Residential Apartments Booked
    203

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    20

  • Covered Car Parking Booked
    143

  • Mechanical Parking Booked
    28

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 5 Under Construction
1 6 Under Construction
1 7 Under Construction
1 8 Under Construction
1 9 Under Construction
1 10 Under Construction
1 11 Under Construction
2 1 Under Construction
2 2 Under Construction
2 3 Under Construction
2 4 Under Construction
2 5 Under Construction
2 6 Under Construction
2 7 Under Construction
2 8 Under Construction
2 9 Under Construction
2 10 Under Construction
2 11 Under Construction
3 1 Under Construction
3 2 Under Construction
3 3 Under Construction
3 4 Under Construction
3 5 Under Construction
3 6 Under Construction
3 7 Under Construction
3 8 Under Construction
3 9 Under Construction
3 10 Under Construction
3 11 Under Construction
3 12 Under Construction
7 1 Under Construction
7 2 Under Construction
7 3 Under Construction
7 4 Under Construction
7 5 Under Construction
7 6 Under Construction
7 7 Under Construction
7 8 Under Construction
7 9 Under Construction
7 10 Under Construction
7 11 Under Construction
7 12 Under Construction
8 1 Under Construction
8 2 Under Construction
8 3 Under Construction
8 4 Under Construction
8 5 Under Construction
8 6 Under Construction
8 7 Under Construction
8 8 Under Construction
8 9 Under Construction
8 10 Under Construction
8 11 Under Construction
8 12 Under Construction
14 1 Under Construction
14 2 Under Construction
14 3 Under Construction
14 4 Under Construction
20 1 Under Construction
20 2 Under Construction
20 3 Under Construction
20 4 Under Construction
20 5 Under Construction
20 6 Under Construction
20 7 Under Construction
20 8 Under Construction
20 9 Under Construction
20 10 Under Construction
20 11 Under Construction
20 12 Under Construction
21 1 Under Construction
21 2 Under Construction
21 3 Under Construction
21 4 Under Construction
21 5 Under Construction
21 6 Under Construction
21 7 Under Construction
21 8 Under Construction
21 9 Under Construction
21 10 Under Construction
21 11 Under Construction
21 12 Under Construction
22 1 Under Construction
22 2 Under Construction
22 3 Under Construction
22 4 Under Construction
22 5 Under Construction
22 6 Under Construction
22 7 Under Construction
22 8 Under Construction
22 9 Under Construction
22 10 Under Construction
22 11 Under Construction
22 12 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Block 8- 1st Phase Plaster, Floor Tiles, Toilet Walls, Kitchen Counter, Fire MS Riser Pipe, Aluminium Window
2 Block 20-Toilet Plumbing, Plumbing Work, Electrical Work, Plaster, Garage Railing, Fire MS Riser Pipe
3 Block 21-Toilet Plumbing, Plumbing Work, Electrical Work, Plaster, Garage Railing, Fire MS Riser Pipe
4
5
6
7 Block- 1 Internal Putty , Flooring, Electric conduct Wire, Aluminium Window, Balcony Railing, Fire Door, Fire Pipe, Flush Door, Kitchen Counter, Lift Facia, Stair Railing., Block - 1
8 Block 2- Internal Putty , Flooring, Electric conduct Wire, Aluminium Window, Balcony Railing, Fire Door, Fire Pipe, Flush Door, Kitchen Counter, Lift Facia, Stair Railing., Block - 2
9 Block 3- Aluminium Window, Marble Flooring, Stair Marble And Flooring, Toilet Wall Tiles, Fire MS Riser , Ground Floor PCC
10 Block 7- 1st Phase Plaster, Floor Tiles, Toilet Walls, Kitchen Counter, Fire MS Riser Pipe
11 Block 22-Toilet Plumbing, Plumbing Work, Electrical Work, Plaster, Garage Railing, Fire MS Riser Pipe

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction POND
2 Under Construction Road
3 Under Construction STP Behind Tower 3
4 Under Construction Under Groung Water Reservoir

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download