West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-12-2019
Updated as on 08-01-2020

Booking Status

  • Residential Apartments Booked
    13

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
2 1 Under Construction
2 2 Under Construction
2 3 Under Construction
2 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Equipment
2 24x7 Security Service
3 Drinking Water Facilities
4 Drainage System
5 Power Back up

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Roof
2 Under Construction Lift
3 Under Construction Lobby
4 Under Construction Septik Tank
5 Under Construction Under Ground water Reservior
6 Under Construction Overload Tank
7 Under Construction Stair case
8 Under Construction Garage

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download