Project Status as on Quarter ending 31-03-2021
Updated as on 16-04-2021

Booking Status

  • Residential Apartments Booked
    33

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    35

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
TOWER 1; RESIDENTAIL 1 Completed With CC
TOWER 1; RESIDENTAIL 2 Completed With CC
TOWER 1; RESIDENTAIL 3 Completed With CC
TOWER 1; RESIDENTAIL 4 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 FLOORING
2 ELECTRICAL
3 PLASTER
4 PLUMBING

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC LAWN
2 Completed With CC LIFT
3 Completed With CC DRIVEWAY
4 Completed With CC STAIRCASE

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download