West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-03-2021
Updated as on 07-04-2021

Booking Status

  • Residential Apartments Booked
    25

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    5

  • Covered Car Parking Booked
    15

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK C, Tower 9 and 10 1 Under Construction
BLOCK C, Tower 9 and 10 2 Under Construction
BLOCK C, Tower 9 and 10 3 Under Construction
BLOCK C, Tower 9 and 10 4 Under Construction
BLOCK C, Tower 9 and 10 5 Under Construction
BLOCK C, Tower 9 and 10 6 Under Construction
BLOCK C, Tower 9 and 10 7 Under Construction
BLOCK C, Tower 9 and 10 8 Under Construction
BLOCK C, Tower 9 and 10 9 Under Construction
BLOCK C, Tower 9 and 10 10 Under Construction
BLOCK C, Tower 9 and 10 11 Under Construction
BLOCK C, Tower 9 and 10 12 Under Construction
BLOCK C, Tower 9 and 10 13 Under Construction
BLOCK C, Tower 9 and 10 14 Under Construction
BLOCK C, Tower 9 and 10 15 Under Construction
BLOCK C, Tower 9 and 10 16 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download