West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 30-06-2021
Updated as on 01-10-2021

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block-1 1 Completed With CC
Block-1 2 Completed With CC
Block-1 3 Completed With CC
Block-1 4 Completed With CC
Block-1 5 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facility
2 Electrical Installation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Underground Water Reservoir
2 Completed With CC Overhead Tank
3 Completed With CC Roof
4 Completed With CC Lift
5 Completed With CC Lobby

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download