West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-03-2021
Updated as on 09-04-2021

Booking Status

  • Residential Apartments Booked
    74

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    6

  • Covered Car Parking Booked
    44

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK -1 1 Not Started
BLOCK -1 2 Not Started
BLOCK -1 3 Not Started
BLOCK -1 4 Not Started
BLOCK -2 (PART -1) 1 Not Started
BLOCK -2 (PART -1) 2 Not Started
BLOCK -2 (PART -1) 3 Not Started
BLOCK -2 (PART -1) 4 Not Started
BLOCK - 2 (PART - 2) 1 Under Construction
BLOCK - 2 (PART - 2) 2 Not Started
BLOCK - 2 (PART - 2) 3 Not Started
BLOCK - 2 (PART - 2) 4 Not Started
BLOCK - 2 (PART - 3) 1 Under Construction
BLOCK - 2 (PART - 3) 2 Under Construction
BLOCK - 2 (PART - 3) 3 Under Construction
BLOCK - 2 (PART - 3) 4 Under Construction
BLOCK -1 1 Under Construction
BLOCK -1 2 Not Started
BLOCK -1 3 Not Started
BLOCK -1 4 Not Started
BLOCK -2 (PART -1) 1 Not Started
BLOCK -2 (PART -1) 2 Not Started
BLOCK -2 (PART -1) 3 Not Started
BLOCK -2 (PART -1) 4 Not Started
BLOCK - 2 (PART - 2) 1 Under Construction
BLOCK - 2 (PART - 2) 2 Under Construction
BLOCK - 2 (PART - 2) 3 Under Construction
BLOCK - 2 (PART - 2) 4 Under Construction
BLOCK - 2 (PART - 3) 1 Under Construction
BLOCK - 2 (PART - 3) 2 Under Construction
BLOCK - 2 (PART - 3) 3 Under Construction
BLOCK - 2 (PART - 3) 4 Under Construction
BLOCK -1 1 Under Construction
BLOCK -1 2 Under Construction
BLOCK -1 3 Under Construction
BLOCK -1 4 Under Construction
BLOCK -2 (PART -1) 1 Under Construction
BLOCK -2 (PART -1) 2 Under Construction
BLOCK -2 (PART -1) 3 Under Construction
BLOCK -2 (PART -1) 4 Under Construction
BLOCK - 2 (PART - 2) 1 Under Construction
BLOCK - 2 (PART - 2) 2 Under Construction
BLOCK - 2 (PART - 2) 3 Under Construction
BLOCK - 2 (PART - 2) 4 Under Construction
BLOCK - 2 (PART - 3) 1 Under Construction
BLOCK - 2 (PART - 3) 2 Under Construction
BLOCK - 2 (PART - 3) 3 Under Construction
BLOCK - 2 (PART - 3) 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1
2 AAC Brick work , 1 to 4th floor completed in block 2 part 3 , 1st floor slab structure completed in block 1, foundation structure completed in block 2 part 1, up to roof structure completed in block 2 part 2
3 BLOCK 1 - 2ND FLOOR SLAB STRUCTURE COMPLETED
4 BLOCK 2 PART 1 - 1ST FLOOR SLAB STRUCTURE COMPLETED
5 BLOCK 2 PART 2 - UPTO ABOVE ROOF STRUCTURE COMPLETED , AAC BLOCK WORK 1ST TO 4TH FLOOR GOING ON
6 BLOCK 2 PART 3 - UPTO ABOVE ROOF STRUCTURE COMPLETED , 1ST TO 4TH AAC BLOCK WORK AND INTERNAL PLASTER GOING ON

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction BLOCK -2 (PART -1)- FOUNDATION WORK
2 Under Construction BLOCK -2 (PART-2) UPTO 1ST FLOOR CASTING
3 Under Construction BLOCK - 2 (PART-3 ) UPTO ABOVE ROOF
4 Not Started not started yet
5 Not Started COMMON AREA WORK NOT STARTED YET FOR THE BLOCK 1, BLOCK 2 PART 1, 2 & 3.

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download