West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 30-09-2021
Updated as on 01-11-2021

Booking Status

  • Residential Apartments Booked
    177

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    48

  • Covered Car Parking Booked
    56

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
2 1 Under Construction
5 2 Under Construction
19 3 Under Construction
1 1 Under Construction
2 1 Under Construction
5 1 Under Construction
19 2 Under Construction
19 1 Under Construction
19 2 Under Construction
19 3 Under Construction
19 4 Under Construction
19 5 Under Construction
5 1 Under Construction
5 2 Under Construction
1 1 Under Construction
2 1 Under Construction
2 1 Under Construction
19 2 Under Construction
19 3 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Elevation of block 5
2 Under Construction Elevation of block 5
3 Under Construction Elevation of block 19

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download