West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-12-2019
Updated as on 07-01-2020

Booking Status

  • Residential Apartments Booked
    86

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    5

  • Covered Car Parking Booked
    8

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block-10A 1 Completed With CC
Block-10A 2 Completed With CC
Block-10A 3 Completed With CC
Block-10A 4 Completed With CC
Block-10A 5 Completed With CC
Block-10A 6 Completed With CC
Block-10A 7 Completed With CC
Block-3A 1 Completed With CC
Block-3A 2 Completed With CC
Block-3A 3 Completed With CC
Block-3A 4 Completed With CC
Block-3A 5 Completed With CC
Block-3A 6 Completed With CC
Block-3A 7 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 3 A
2 10 A

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Ground Lobby (Block-3A)
2 Completed With CC Car Park (Block-3A)
3 Completed With CC Ground Lobby (Block-10A)
4 Completed With CC Car Park (Block-10A)
5 Completed With CC Roof (Block-10A)
6 Completed With CC Roof (Block-10A)
7 Completed With CC Roof (Block-10A)

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download