Project Status as on Quarter ending 31-12-2021
Updated as on 25-01-2022

Booking Status

  • Residential Apartments Booked
    44

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    44

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Villa -1 G+2 2 Completed With CC
Villa - 2 G+2 2 Under Construction
Villa - 3 G+2 2 Completed With CC
Villa - 4 G+2 2 Completed With CC
Villa - 5 G+2 2 Completed With CC
Villa - 6 G+2 2 Completed With CC
Villa - 7 G+2 2 Completed With CC
Villa - 8 G+2 2 Completed With CC
Villa - 9 G+2 2 Completed With CC
Villa - 10 G+2 2 Completed With CC
Villa -11 G+2 2 Under Construction
Villa - 12 G+2 2 Under Construction
Villa - 14 G+2 2 Completed With CC
Villa - 15 G+2 2 Completed With CC
Villa - 16 G+2 2 Completed With CC
Villa - 17 G+2 2 Completed With CC
Villa - 18 G+2 2 Completed With CC
Villa -19 G+2 2 Completed With CC
Villa - 20 G+2 2 Completed With CC
Villa -21 G+2 2 Under Construction
Villa - 22 G+2 2 Under Construction
Villa - 23 G+2 2 Under Construction
Villa - 24 G+2 2 Under Construction
Villa - 25 G+2 2 Under Construction
Villa - 26 G+2 2 Under Construction
Villa - 27 G+2 2 Under Construction
Villa - 28 G+2 2 Under Construction
Villa - 29 G+2 2 Completed With CC
Villa - 30 G+2 2 Completed With CC
Villa - 31 G+2 2 Completed With CC
Villa - 32 G+2 2 Completed With CC
Villa - 33 G+2 2 Completed With CC
Villa - 34 G+2 2 Completed With CC
Villa - 35 G+2 2 Completed With CC
Villa - 36 G+2 2 Completed With CC
Villa - 37 G+2 2 Completed With CC
Villa - 38 G+2 2 Completed With CC
Villa - 39 G+2 2 Completed With CC
Villa - 43 G+2 2 Completed With CC
Villa - 44G+2 2 Completed With CC
Villa - 45 G+2 2 Completed With CC
Villa - 46 G+2 2 Completed With CC
Villa - 47 G+2 2 Completed With CC
Villa -48 G+2 2 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Common Area - Road

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 01-02-2020 19-02-2020 19-02-2020
Such other approvals as may be required and obtained for the project 01-11-2020 25-11-2020 25-11-2020 REVISED MASTER LAYOUT PLAN