Project Status as on Quarter ending 31-12-2020
Updated as on 19-01-2021

Booking Status

  • Residential Apartments Booked
    25

  • Basement Parking Booked
    16

  • Open Car Parking Booked
    9

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    22

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 23 Under Construction
1 23 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Finishing Works in Progress
2 Various Finishing Work in progress
3 various Finishing WIP
4 Finishing WIP
5 Finishing WIP
6 Finishing WIP
7 Finishing WIP
8 Finishing WIP
9 Aluminium Fabrication
10 Brickwork
11 Electrical wip
12 Firefighting work
13 Flooring
14 Plastering work
15 Plumbing
16 HVAC wip
17 Tiling

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Driveway, Main Gate & Boundry wall
2 Under Construction Drive way & main Gate WIP
3 Under Construction External Brickwork, Plaster & Plumbing WIP
4 Under Construction External B.work, Plaster & ramp WIP.
5 Under Construction External Paint in Progress
6 Under Construction Parking & landscaping WIP
7 Under Construction Electrical & Landscaping WIP
8 Under Construction Waterbody
9 Under Construction Gate no - 2
10 Under Construction Front Side boundary wall

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 04-01-2016 31-03-2016 18-02-2015
Fire NOC 25-02-2015 31-08-2021 12-08-2021
Other 29-04-2014 31-10-2014 13-01-2021