West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 30-09-2019
Updated as on 19-10-2019

Booking Status

  • Residential Apartments Booked
    71

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    57

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
G 1 Under Construction
G 2 Under Construction
G 3 Under Construction
G 4 Under Construction
H 1 Not Started
H 2 Not Started
H 3 Not Started
H 4 Not Started
I 1 Under Construction
I 2 Under Construction
I 3 Under Construction
I 4 Under Construction
J 1 Under Construction
J 2 Under Construction
J 3 Under Construction
J 4 Under Construction
K 2 Under Construction
K 3 Under Construction
K 4 Under Construction
K 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 ELECTRIC INSTALLATION
2 FIRE FIGHTING FACILITY
3 DRIKING WATER FACILITY

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction LIFT
2 Under Construction LOBBY
3 Under Construction SEPTIC TANK
4 Under Construction WATER RESERVIOR
5 Under Construction ROOF

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download