West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-03-2021
Updated as on 20-07-2021

Booking Status

  • Residential Apartments Booked
    40

  • Commercial Unit Booked
    2

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    28

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - 1 (Ground Floor - G+1)Com. & 2nd to 4th (R 1 Under Construction
Block - 1 (Ground Floor - G+1)Commercial 1 Under Construction
Block - 2 (Floor - 1) Com.& 2nd to 4th (Res.) 1 Under Construction
Block - 2 (Floor - 1) Com.& 2nd to 4th (Res.) 2 Under Construction
Block - 2 (Floor - 1) Com.& 2nd to 4th (Res.) 3 Under Construction
Block - 2 (Floor - 1) Com.& 2nd to 4th (Res.) 4 Under Construction
Block - 2 (Floor - 1) Com.& 2nd to 4th (Res.) 2 Under Construction
Block - 2 (Floor - 1) Com.& 2nd to 4th (Res.) 3 Under Construction
Block - 2 (Floor - 1) Com.& 2nd to 4th (Res.) 4 Under Construction
Block - 2 (Ground Floor - G+1) Commercial 1 Under Construction
Block - 3 1 Under Construction
Block - 3 2 Under Construction
Block - 3 3 Not Started
Block - 3 4 Not Started
Block-4 1 Under Construction
Block-4 2 Under Construction
Block-4 3 Under Construction
Block-5 4 Not Started
Block-6 4 Not Started
Block-7 4 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download