West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 30-06-2021
Updated as on 06-09-2021

Booking Status

  • Residential Apartments Booked
    514

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    336

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 5 1 Under Construction
Tower 6 1 Under Construction
Tower 7 1 Under Construction
Tower 13 1 Under Construction
Tower 14 1 Under Construction
Tower 15 1 Under Construction
Tower 16 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 BOUNDARY WALL
2 CABLE TREANCH
3 ROAD
4 UGR STP
5 RAIN WATER HERVESTING TANK

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction NON TOWER AREA

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Fire NOC 06-11-2020 28-02-2021 19-02-2021
Height clearance from Airport Authority of India (if any) 02-03-2021 31-03-2021 17-03-2021
Environmental Clearance 21-09-2019 31-03-2020 21-12-2020