West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-12-2021
Updated as on 18-01-2022

Booking Status

  • Residential Apartments Booked
    33

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    7

  • Covered Car Parking Booked
    6

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
19 1 Under Construction
19 2 Under Construction
19 3 Not Started
19 4 Not Started
19 5 Not Started
19 6 Not Started
19 7 Not Started
19 8 Not Started
19 9 Not Started
19 10 Not Started
19 11 Not Started
19 12 Not Started
19 13 Not Started
20 1 Not Started
20 2 Not Started
20 3 Not Started
20 4 Not Started
20 5 Not Started
20 6 Not Started
20 7 Not Started
20 8 Not Started
20 9 Not Started
20 10 Not Started
20 11 Not Started
20 12 Not Started
20 13 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facility
2 Water Filter Plant

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Stairs
2 Not Started Lobby
3 Under Construction Power Backup
4 Not Started Septic Tank
5 Not Started Roof
6 Not Started Lift
7 Under Construction Club
8 Not Started Overhead Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download