West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-12-2020
Updated as on 21-10-2020

Booking Status

  • Residential Apartments Booked
    291

  • Basement Parking Booked
    226

  • Open Car Parking Booked
    131

  • Covered Car Parking Booked
    24

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Plumbing , Sanitary , Drainage , swerage works are under progress and will be completed shortly

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Ground Floor & Typical floor , Lift Lobby , total amenities zone including swimming pool and Land scape in under progress and will be completed shortly

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download