West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-12-2021
Updated as on 24-01-2022

Booking Status

  • Residential Apartments Booked
    186

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    220

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 5 Under Construction
1 6 Under Construction
1 7 Under Construction
1 8 Under Construction
1 9 Under Construction
1 10 Under Construction
1 11 Under Construction
1 12 Under Construction
1 13 Under Construction
1 14 Under Construction
1 15 Under Construction
1 16 Under Construction
1 17 Under Construction
1 18 Under Construction
1 19 Under Construction
1 20 Under Construction
1 21 Under Construction
1 22 Under Construction
1 23 Under Construction
1 24 Under Construction
1 25 Under Construction
1 26 Under Construction
1 27 Not Started
1 28 Not Started
1 29 Not Started
1 30 Not Started
1 31 Not Started
2 2 Under Construction
2 3 Under Construction
2 4 Under Construction
2 5 Under Construction
2 6 Under Construction
2 7 Under Construction
2 8 Under Construction
2 9 Under Construction
2 10 Under Construction
2 11 Under Construction
2 12 Under Construction
2 13 Under Construction
2 14 Under Construction
2 15 Under Construction
2 16 Under Construction
2 17 Under Construction
2 18 Under Construction
2 19 Under Construction
2 20 Under Construction
2 21 Under Construction
2 22 Under Construction
2 23 Under Construction
2 24 Under Construction
2 25 Under Construction
2 26 Under Construction
2 27 Under Construction
2 28 Under Construction
2 29 Under Construction
2 30 Under Construction
2 31 Under Construction
3 1 Under Construction
3 2 Under Construction
3 3 Under Construction
3 4 Under Construction
3 5 Under Construction
3 6 Under Construction
3 7 Under Construction
3 8 Under Construction
3 9 Under Construction
3 10 Under Construction
3 11 Under Construction
3 12 Under Construction
3 13 Under Construction
3 14 Under Construction
3 15 Under Construction
3 16 Under Construction
3 17 Under Construction
3 18 Under Construction
3 19 Under Construction
3 20 Under Construction
3 21 Under Construction
3 22 Under Construction
3 23 Under Construction
3 24 Under Construction
3 25 Under Construction
3 26 Under Construction
3 27 Under Construction
3 28 Under Construction
3 29 Under Construction
3 30 Under Construction
3 31 Under Construction
2 1 Under Construction
4 1 Not Started
4 2 Not Started
4 3 Not Started
4 4 Not Started
4 5 Not Started
4 6 Not Started
4 7 Not Started
4 8 Not Started
4 9 Not Started
4 10 Not Started
4 11 Not Started
4 12 Not Started
4 13 Not Started
4 14 Not Started
4 15 Not Started
4 16 Not Started
4 17 Not Started
4 18 Not Started
4 19 Not Started
4 20 Not Started
4 21 Not Started
4 22 Not Started
4 23 Not Started
4 24 Not Started
4 25 Not Started
4 26 Not Started
4 27 Not Started
4 28 Not Started
4 29 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 FIRE FIGHTING FACILITIES
2 WATER FILTERATION PLANT
3 ELECTRICAL INSTALLATION

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction CLUB
2 Not Started SKYWALK
3 Not Started SOLAR LIGHTING
4 Not Started POWER BACKUP
5 Under Construction LIFT
6 Under Construction LOBBY
7 Not Started ROOF
8 Not Started SEPTIC TANK
9 Not Started UNDER-GROUND WATER RESERVOIR
10 Not Started OVERHEAD TANK
11 Under Construction STAIRS

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download