West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-12-2019
Updated as on 05-01-2020

Booking Status

  • Residential Apartments Booked
    6

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    3

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Standalone Building (Residential) 3 Under Construction
Standalone Building (Residential) 4 Under Construction
Standalone Building (Commercial) 1 Under Construction
Standalone Building (Residential) 1 Under Construction
Standalone Building (Residential) 2 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Standalone G+4 Building - Inside Room and Kicthen
2 Standalone G+4 Building - Stair Case

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Entrance Drive way
2 Under Construction Standalone G+4 Building - Lift and Machine Room and Satire case

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download