Project Status as on Quarter ending 30-09-2021
Updated as on 08-10-2021

Booking Status

  • Residential Apartments Booked
    2089

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    1537

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 1 14 Under Construction
Tower 2 14 Under Construction
Tower 3 14 Under Construction
Tower 4 14 Under Construction
Tower 5 14 Under Construction
Tower 6 14 Under Construction
Tower 7 14 Under Construction
Tower 8 14 Under Construction
Tower 9 14 Under Construction
Tower 10 14 Under Construction
Tower 11 14 Under Construction
Tower 12 14 Under Construction
Tower 22 10 Under Construction
Tower 24 10 Under Construction
Tower 23 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Underground Reservoir

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Pilling work completed for Cluster F(Tower 16,17,18)
2 Under Construction Pilling work completed and sub structure work in progress for Cluster E(Tower 13,14,15)
3 Under Construction Pilling work completed for Cluster G( Tower 19,20,21)

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download