1 |
BLOCK -I, ALL STRUCTURE COMPLETED UPTO ABOVE ROOF , UGF TO 9TH FLOOR INTERNAL PLASTER COMPLETED, UGF TO 7TH FLOOR INTERNAL PUTTY COMPLETED. |
|
2 |
BLOCK -II, ALL STRUCTURE COMPLETED UPTO ABOVE ROOF , 1ST TO 15TH FLOOR AAC BLOCK WORK COMPLETED, 1ST TO 8TH FLOOR INTERNAL PLASTER WORK COMPLETED. |
|
3 |
BLOCK-III, ALL STRUCTURE COMPLETED UP TO ABOVE ROOF, 1ST TO 15TH FLOOR AAC BLOCK WORK COMPLETED, 1ST TO 15TH INTERNAL PLASTER WORK COMPLETED, 70% OF 4 SIDES EXTERNAL PLASTER WORK COMPLETED |
|
4 |
BLOCK - IV , UPTO 9TH FLOOR STRUCTURE COMPLETED , UGF TO 3RD FLOOR AAC BLOCK WORK COMPLETED |
|
5 |
Block - 1, up to above roof - All Structure completed except overhead water tank wall & Top Slab |
|
6 |
Block- 2, Up to above Roof - All Structures completed except Overhead water tank wall & Top Slab |
|
7 |
Block-3, Up to above roof - All Structures completed except overhead water tank wall & top slab |
|
8 |
Block-4, Up to 7th floor - Structure completed |
|
9 |
BLOCK - I , AAC BLOCK WORK ( UGF TO 9TH FLOOR COMPLETED ) |
|
10 |
BLOCK - I , INTERNAL PLASTER ( UGF TO 3RD FLOOR COMPLETED ) |
|
11 |
BLOCK - II , AAC BLOCK WORK ( 1ST TO 8TH FLOOR COMPLETED ) |
|
12 |
BLOCK II , INTERNAL PLASTER |
|
13 |
BLOCK -III , AAC BLOCK WORK ( 1ST TO 13TH FLOOR COMPLETED ) |
|
14 |
BLOCK - III , INTERNAL PLASTER ( 1ST & 4TH FLOOR COMPLETED ) |
|
15 |
BLOCK - IV , AAC BLOCK WORK ( UGF TO 1ST FLOOR COMPLETED ) |
|
16 |
BLOCK - IV , INTERNAL PLASTER |
|