West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 30-09-2021
Updated as on 01-10-2021

Booking Status

  • Residential Apartments Booked
    932

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
SPANDAN (LIG) PHASE 8 4 Under Construction
SPANDAN (LIG) PHASE 8 1 Under Construction
SPANDAN (LIG) PHASE 8 2 Under Construction
SPANDAN (LIG) PHASE 8 3 Under Construction
SPANDAN (LIG) PHASE 8 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Road network
2 Road network
3 Internal plumbing work

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 04-11-2014 16-01-2015 16-01-2015
Consent to Establish and Operate 28-03-2006 22-01-2009 22-01-2009