West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-03-2021
Updated as on 01-04-2021

Booking Status

  • Residential Apartments Booked
    11

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    7

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
TOWER I 1 Under Construction
TOWER I 2 Under Construction
TOWER I 3 Under Construction
TOWER I 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 INTERNAL INFRASTRUCTURE

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction COMMON AREA

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download