West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-03-2021
Updated as on 26-08-2021

Booking Status

  • Residential Apartments Booked
    9

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    2

  • Covered Car Parking Booked
    4

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - 1 Residential 1 Under Construction
Block - 1 Residential 2 Completed With CC
Block - 1 Residential 3 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Entrance

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Parking

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download