West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-03-2021
Updated as on 20-06-2021

Booking Status

  • Residential Apartments Booked
    27

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
A 1 Under Construction
A 2 Under Construction
A 3 Under Construction
A 4 Under Construction
B 1 Under Construction
B 2 Under Construction
B 3 Under Construction
B 4 Under Construction
C 1 Under Construction
C 2 Under Construction
C 3 Under Construction
C 4 Under Construction
D 1 Under Construction
D 2 Under Construction
D 3 Under Construction
D 4 Under Construction
E 1 Under Construction
E 2 Under Construction
E 3 Under Construction
E 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download