West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 30-09-2021
Updated as on 01-12-2021

Booking Status

  • Residential Apartments Booked
    153

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    42

  • Covered Car Parking Booked
    85

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 1 Under Construction
Block 1 2 Under Construction
Block 1 3 Under Construction
Block 2 1 Under Construction
Block 2 2 Under Construction
Block 2 3 Under Construction
Block 2 4 Under Construction
Block 2 5 Under Construction
Block 2 6 Under Construction
Block 2 7 Under Construction
Block 2 8 Not Started
Block 2 9 Not Started
Block 2 10 Not Started
Block 3 1 Under Construction
Block 3 2 Under Construction
Block 3 3 Under Construction
Block 3 4 Under Construction
Block 3 5 Under Construction
Block 3 6 Under Construction
Block 3 7 Under Construction
Block 3 8 Not Started
Block 3 9 Not Started
Block 3 10 Not Started
Block 4 1 Under Construction
Block 4 2 Under Construction
Block 4 3 Under Construction
Block 4 4 Under Construction
Block 4 5 Under Construction
Block 4 6 Under Construction
Block 4 7 Under Construction
Block 4 8 Under Construction
Block 4 9 Under Construction
Block 4 10 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 FIRE FIGHTING FACILITIES
2 WATER FILTERATION PLANT
3 ELECTRICAL INSTALLATION

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started CLUB
2 Not Started POWER BACKUP
3 Not Started LIFT
4 Under Construction LOBBY
5 Under Construction ROOF
6 Under Construction OVERHEAD TANK
7 Not Started SEPTIK TANK
8 Not Started UNDER GROUND WATER RESERVOIR
9 Under Construction STAIRS

Approval for NOC