Project Status as on Quarter ending 30-09-2020
Updated as on 21-11-2020

Booking Status

  • Residential Apartments Booked
    170

  • Basement Parking Booked
    1

  • Open Car Parking Booked
    62

  • Covered Car Parking Booked
    79

  • Mechanical Parking Booked
    34

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
9 1 Under Construction
9 2 Under Construction
9 3 Under Construction
9 4 Under Construction
9 5 Under Construction
9 6 Under Construction
9 7 Under Construction
9 8 Under Construction
9 9 Under Construction
9 10 Under Construction
9 11 Under Construction
9 12 Under Construction
9 13 Under Construction
9 14 Under Construction
10 1 Under Construction
10 2 Under Construction
10 3 Under Construction
10 4 Under Construction
10 5 Under Construction
10 6 Under Construction
10 7 Under Construction
10 8 Under Construction
10 9 Under Construction
10 10 Under Construction
10 11 Under Construction
10 12 Under Construction
10 13 Under Construction
10 14 Under Construction
14 1 Under Construction
14 2 Under Construction
14 3 Under Construction
14 4 Under Construction
14 5 Under Construction
14 6 Under Construction
14 7 Under Construction
14 8 Not Started
14 9 Not Started
14 10 Not Started
14 11 Not Started
14 12 Not Started
14 13 Not Started
14 14 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilites
2 Electrical Installation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lift
2 Under Construction Lobby
3 Under Construction Roof
4 Under Construction Septic tank
5 Under Construction Under-ground water reservoir
6 Under Construction Overhead tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download