Project Status as on Quarter ending 30-06-2019
Updated as on 24-07-2019

Booking Status

  • Residential Apartments Booked
    168

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    3

  • Covered Car Parking Booked
    78

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Not Started Swimming Pool

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download