West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 31-12-2019
Updated as on 10-01-2020

Booking Status

  • Residential Apartments Booked
    148

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    80

  • Covered Car Parking Booked
    53

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
A 1 Completed With CC
A 2 Completed With CC
A 3 Completed With CC
A 4 Completed With CC
A 5 Completed With CC
A 6 Completed With CC
A 7 Completed With CC
A 8 Completed With CC
A 9 Completed With CC
A 10 Completed With CC
A 11 Completed With CC
B 1 Completed With CC
B 2 Completed With CC
B 3 Completed With CC
B 4 Completed With CC
B 5 Completed With CC
B 6 Completed With CC
B 7 Completed With CC
B 8 Completed With CC
B 9 Completed With CC
B 10 Completed With CC
B 11 Completed With CC
C 1 Completed With CC
C 2 Completed With CC
C 3 Completed With CC
C 4 Completed With CC
C 5 Completed With CC
C 6 Completed With CC
C 7 Completed With CC
C 8 Completed With CC
C 9 Completed With CC
C 10 Completed With CC
C 10 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Plumbing with fixtures, Flooring, Electrical Services, Aluminium Windom, Door Shutters with locks, POP

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Lift, Club, Gym, Lobby.

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download