West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 30-09-2021
Updated as on 06-10-2021

Booking Status

  • Residential Apartments Booked
    150

  • Basement Parking Booked
    Not mentioned

  • Open Car Parking Booked
    49

  • Covered Car Parking Booked
    63

  • Mechanical Parking Booked
    34

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
UDVITA: WING-A 1 Completed With CC
UDVITA: WING-A 3 Completed With CC
UDVITA: WING-A 4 Completed With CC
UDVITA: WING-A 5 Completed With CC
UDVITA: WING-A 6 Completed With CC
UDVITA: WING-A 7 Completed With CC
UDVITA: WING-A 8 Completed With CC
UDVITA: WING-A 9 Completed With CC
UDVITA: WING-A 10 Completed With CC
UDVITA: WING-A 11 Completed With CC
UDVITA: WING-A 12 Completed With CC
UDVITA: WING-B 1 Completed With CC
UDVITA: WING-B 2 Completed With CC
UDVITA: WING-B 3 Completed With CC
UDVITA: WING-B 4 Completed With CC
UDVITA: WING-B 5 Completed With CC
UDVITA: WING-B 6 Completed With CC
UDVITA: WING-B 7 Completed With CC
UDVITA: WING-B 8 Completed With CC
UDVITA: WING-B 9 Completed With CC
UDVITA: WING-B 10 Completed With CC
UDVITA: WING-B 11 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 24/7 DG Facility
2 Provison for Service Elevator
3 Water Treatment Plant
4 Internal Road

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Residential Activity Centre
2 Completed With CC Area Landscaping
3 Completed With CC Street Lighting
4 Completed With CC Light in Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 18-02-2019 28-03-2019 28-03-2019
Fire NOC 12-01-2020 06-02-2020 06-04-2020 FIRE NOC RENEWAL