West Bengal Housing Industry Regulatory Authority

WBHIRA

Project Status as on Quarter ending 30-09-2020
Updated as on 07-10-2020

Booking Status

  • Residential Apartments Booked
    79

  • Basement Parking Booked
    28

  • Open Car Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    64

  • Mechanical Parking Booked
    4

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 1(B+G+12) 1 Under Construction
Tower 2 (B+G+12) 1 Under Construction
Tower 3 (B+G+12) 1 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drainage and Road

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 24-06-2019 30-06-2019 08-07-2019